Version History
- Exply 4.19.0 - Calculation Part 2, Collapsable Pivot Table & Bugfixes (10th Feb 2021)
- Exply 4.18.0 - Map Widget, WYSIWYG Text Editor , Linear Trend Lines (17th December 2020)
- Exply 4.17.1 - Issue Age, Improved Process Management & Logging (13th October 2020)
- Exply 4.17.0 - Partly On-Demand Jira Imports, Separate Sum Bar, Comparisons in Metric Tiles
- Exply 4.16.1 - Tempo Account Bugfixes & Further Improvements (23rd July 2020)
- Exply 4.16.0 - Pivot Table Improvements, Calculations Part 1.5 & Improvements (3rd July 2020)
- Exply 4.15.0 - Average, Min, Max, Ignore Time Selection (17th June 2020)
- Exply 4.14.0 - Custom Exply for Jira Importer Schedule & Improvements (29th May 2020)
- Exply 4.13.1 - Changes are visible immediately after Data Import (13rd May 2020)
- Exply 4.13.0 - Calculation (Phase 1), Reference Lines (30th April 2020)
- Exply 4.12.0 - Sprint Detection, Value Filter, Units, Tempo Team Programs (3rd Apr 2020)
- Exply 4.11.0 - Raw Data Table filter & Improvements (17th Mar 2020)
- Exply 4.10.1 - Burn Down Chart & Windows Server Improvements (05th Mar 2020)
- Exply 4.10.0 - Define import period, Tempo Workloads & Commitment (26th Feb 2020)
- Exply 4.9.1 - Improvements (18th Feb 2020)
- Exply 4.9.0 - Tempo Revenue & Bugfixes (12th Feb 2020)
- Exply 4.8.3 - Improvements & Bugfixes (4th Feb 2020)
- Exply 4.8.2 - New Booked/Estimated Ratio value field & many Improvements (22nd Jan 2020)
- Exply 4.8.1 - Importer Performance Improvements & Tempo Teams (18th Dec 2019)
- Exply 4.8.0 - Generic SQL-Importer, Federated Jira, Quick Filter Widget, Tempo Improvements (6th Dec 2019)
- Exply 4.7.0 - Customisable CSV Import (15th Nov 2019)
- Exply 4.6.1 - Microsoft SQL Server Support (16th Oct 2019)
- Exply 4.6.0 - Java 11 Support (15th Oct 2019)
- Exply 4.5.0 - Gantt Chart and more Fields (10th Oct 2019)
- Exply 4.4.0 - New Dashboard Screen and Jira Fields (26th September 2019)
- Exply 4.3.1 - Name and Email of Creator for all Work Logs (13th September 2019)
- Exply 4.3.0 - Import status changes of Jira issues (12th September 2019)
- Exply 4.2.0 - Widget Explorer (10th September 2019)
- Exply 4.1.0 - User Management for JIRA & Excel Export Permission (4th September 2019)
- Exply 4.0.0 - Major Release (28th August 2019)
- Exply 3.22.0 - Tempo Importer Improvements & Bugfixes (25th July 2019)
- Exply 3.21.1 - Improvements & Bugfixes (11th July 2019)
- Exply 3.21.0 - Legend Option for Bar/Row Charts & Bugfixes (24th May 2019)
- Exply 3.20.1 - Multi-Value Time Series Chart & Bugfixes (2nd May 2019)
- Exply 3.19.1 - Minor Fixes & Improvements (12th April 2019)
- Exply 3.19.0 - New Time Selector & Improvements (5th April 2019)
- Exply 3.18.0 - Support for JIRA Gadgets & more default Dashboards (20th February 2019)
- Exply 3.17.5 - JIRA 8 Compatibility & Bugfixes (13th February 2019)
- Exply 3.17.4 - Minor Improvements & Bugfixes (30th January 2019)
- Exply 3.17.3 - Minor Improvements & Bugfixes (8th January 2019)
- Exply 3.17.2 - Treemap Widget Labels & Bugfixes (5th December 2018)
- Exply 3.17.1 - Bugfixes & Improvements (16th November 2018)
- Exply 3.17.0 - Selectable Timeline Chart, Improved Quota Tile, Pivot-Functionality for Bar Charts, Line Chart, Scatter Plot (12th November 2018)
- Exply 3.16.1 - Styling and Usability Improvements (18th October 2018)
- Exply 3.16.0 - Sunburst Pie Widget, CSV Import & new Metrics Tile Options (8th October 2018)
- Exply 3.15.0 - Treemap Widget & Improvements (12th September 2018)
- Exply 3.14.0 - Matrix Chart & CSV-Import (Preview) (4th September 2018)
- Exply 3.13.0 - Tooltips & more Help (13th August 2018)
- Exply 3.12.2 - New Quota Tile Feature & Improvements (31th July 2018)
- Exply 3.12.1 - Minor Fixes & Improvements (24th July 2018)
- Exply 3.12.0 - Improved Usability, Speed & Design (6th July 2018)
- Exply 3.11.0 - Multi-Value Row Charts (28th May 2018)
- Exply 3.10.2 - Improved Handling of Tempo Custom Fields (8th May 2018)
- Exply 3.10.1 - Minor fix for some Field IDs (4th May 2018)
- Exply 3.10.0 - Support for all JIRA Custom Fields (3rd May 2018)
- Exply 3.9.0 - Table Widget (24 April 2018)
- Exply 3.8.0 - Guided Tour & Windows Host Fix (17th April 2018)
- Exply 3.7.1 - Critical JIRA Bugfix (6th April 2018)
- Exply 3.7.0 - New Filters & Bugfixes (19th March 2018)
- Exply 3.6.1 - Improvements (23th February 2018)
- Exply 3.6.0 - Raw Data Export (22 February 2018)
- Exply 3.5.0 - Excel Export (12th February 2018)
- Exply 3.4.0 - More Operators, Filters, Full-Text Search, Improved User Management (2nd February 2018)
- Exply 3.3.0 - Image Widget & Custom Quota Tile Color (6th December 2017)
- Exply 3.2.0 - Production Release (27th November 2017)
- Exply 3.1.0 - Better JIRA Integration and much more (29th June 2017)
- Exply 3.0.4 - Importer & Stability Improvements (5th May 2017)
- Exply 3.0.3 - Auto-Recovery (27th April 2017)
- Exply 3.0.2 - UX/UI Improvements (7th April 2017)
- Exply 3.0.1 - Minor Bugfixes (30th March 2017)
- Exply 3.0.0 - Initial Release (8th March 2017)
Exply 4.19.0 - Calculations Part 2, Collapsable Pivot Table & Bugfixes
Highlights:
- It is now possible to multiply or divide one value field by another value field or constant.
- Added a new collapse function to the Pivot Table widget.
- Within the Display options, you can now decide whether or not your Pivot Groups should be collapsed per default and for which groups this applies.
Improvements:
- Duplicating a favourite Dashboard will now also results in a favourite Dashboard copy
- Redesigned the "Edit" Button in Dashboards to be more noticeable
- Improved the value naming in the Burn Down Chart legend description. Guideline is now called Target Remaining and Remaining is called Actual Remaining.
- Improved the Welcome Screen Buttons
- Improved the error handling within the Jira importer to collect exceptions and show them in the logs instead of stopping the whole import process
- Within the Jira Importer Configuration screen changes get automatically saved without the need to click the save button
- Fixed a bug that prevented users from setting a Value Field to Number of Entries
- The Widget Editor now does respect time selector from global widget groups
- The Widget Editor now also respects "All Time" selections in the Time Selector
- Fixed a bug that caused dropdown fields from the Quick Filter to stay behind other widgets
- Fixed a bug in the Calculations feature, that caused operators to show up again after being changed
- Fixed a bug that prevented users from de/activate Data Source Importers
- Fixed a bug that sometimes did not refresh Dashboard data
- Fixed a bug that sometimes caused the Importer status to not being shown
- Fixed a bug that caused previews in the widget configuration to not update when a field was changed back to its origin value
- Fixed a bug that caused the Exply UI to crash when users tried to download the importer logs without having permissions
Exply 4.18.0 - Map Widget, WYSIWYG Text Editor , Linear Trend Lines
Features:
- Row and Bar Charts have a new option to hide further values.
- Linear trendlines can be added to any Time Series Chart
- Added support for the following Jira Service Desk fields: Customer Request Type Field, SLA Fields
- Added new Map Widget (supports Geo Points)
- Added WYSIWYG text editor to the Spacer Widget
- Widgets can now be resized at every edge and side


Improvements:
- Added compatibility for the upcoming release of Tempo 11
- Fixed some styling glitches that could appear on Dashboards
- Fixed a bug with the license upload in Exply On-Premise
- Removed the favourite Dashboards section, if no Dashboards have been favoured
- Within the Widget Explorer, the Category and Date section have been switched
- Fixed some small bugs in the Widget Explorer
Exply 4.17.1 - Issue Age, Improved Process Management & Logging
Features:
- Exply now also imports the Issue Age in days
Improvements:
- Process Management with UUID-Files: makes the management of exply process hopefully way more stable
BUGFIX/FEATURE: Metric Tile Comparisons behave now more like the user would expect - The logging of the Jira Importer has been greatly improved
- Fixed a small usability issue that prevented users from starting the Jira Importer again after it failed.
- Fixed an issue that caused the data index to be deleted when only a few projects where imported with the Jira Importer Widget (Please note that this feature is still considered to be alpha)
Exply 4.17.0 - Partly On-Demand Jira Imports, Separate Sum Bar, Comparisons in Metric Tiles
Highlight:
- To greatly reduce the import time you can now start on-demand partly imports via the Importer Status Widget. By default Exply imports new data at night (or whatever schedule has been selected). Depending on the amount of data (projects, issues, logged hours, etc.) this can take a while. If users have made last-minute-changes to their data, this is only displayed after a new import in Exply.
- How it works:
- Add the Importer Status Widget to your desired Dashboard
- Select which of your projects you want to import (update their data) and within which period
- Also select if you want to import project unrelated data, e.g. Sprints, Tempo workload, Tempo Team Commitment
- Start your import :)
- Known Issues:
- This is an alpha feature which will need a lot of testing and some tweaks. Any feedback is highly welcome - support@exply.io :)
- There is no progress bar yet
- If another import is already running, you will not be able to start yours - you will need to try it again later.
- How it works:

Exply for Jira On Demand Data Import
Features:
- The Exply for Jira Importer Configuration Screen has been redesigned to be more user friendly.
- Bar & Row Charts now have a new option to also show a separate sum bar. Please note: This option does not yet work if stacking is used.
- Metric Tiles have got new (beta) options to show comparisons with the previous period/previous year.
Improvements:
- Fixed a bug that caused the Exply importer to not work correctly if database had a different collation
- Greatly improved the behaviour of the autocompletion in filters, value/date/category fields
- Fixed a bug that caused the Exply importer to crash if it could not import a certain custom field
Exply 4.16.1 - Tempo Account Bugfixes & Further Improvements
Improvements:
- Added a new option for relative time selection to the Time Selector Widget. You can now set an individual number of days to view your data, e.g. last 30 days.
- Fixed a bug that caused logged hours to have no Tempo accounts if only the project issues have been linked to the Tempo account.
- Fixed a bug that has set the default importer schedule to "monthly" instead of "daily".
- Fixed a visual bug that caused the new bar that shows applied widget group filters in display mode to not be at the right place in PDF exports and Jira gadgets.
- Improved the UI stack trace to be more helpful.
Exply 4.16.0 - Pivot Table Improvements, Calculations Part 1.5 & Improvements
Features:
- Pivot Table entries are now selectable and work also as temporary filters as other widgets do
- If you have set filters for widget groups they are now also displayed in the dashboard view mode, so that you see at a glance which filters are active.
- Calculation Part 1.5: You can now also multiply and divide two value fields. Please note that there is one small restriction right now: This is only possible when both value fields never contain an empty field. This will be covered in Calculation Part 2.
- Time Series Charts now feature individual date fields per chat group.
Improvements:
- Restyled the Pivot Table to be more appealing
- Fixed a bug that stopped the importer from working when Tempo Teams where inherited
- Fixed a bug that caused Exply in very rare cases to not being fully removed during an update and therefore prevented the new Exply version from working correctly.
Exply 4.15.0 - Average, Min, Max, Ignore Time Selection
Features:
- Exply now provides AVERAGE, MIN & MAX as new analysis modes! They are available in the following widgets: Bar Chat, Row, Chart, Scatter Plot, Matrix Chart, Time Series Charts, Pivot Table, Metric Tile. To add them, simply click "Add calculation" beneath the selected Value Field. The Average works per day, month, year and any other category field you have.
- New option to ignore the time selection in a widget. Sometimes data has no time reference, e.g. statistical data, static data, etc. To view or compare them with time-based data you simply select "Ignore Time Selection" as Date Field.
Improvements:
- Redesigned the Display Options section to be clearer, user-friendlier, and more appealing
- Fixed an issue that caused new widgets to show "No Data" after adding them via the Widget Explorer

Average in Exply

Ignore Time Selection for Data
Exply 4.14.0 - Custom Exply for Jira Importer Schedule & Improvements
Features:
- Custom import scheduling for Exply for JIRA. Per default, the data import happens in the middle of the night, so that everything is updated in the morning. In some cases, this update rhythm is too slow. We, therefore, implemented the custom import schedule. There are a couple of presets to choose from or you can set it to your specific needs via crontab.
- Bar & Row Chart widgets have a new powerful feature to only show secondary values where the primary value has data. For example, you want to compare the Tempo Workload Hours of certain team members with the sum of estimates of the issues they are assigned to. The 1st Value Field would be Workload Hours of Team Members of a certain team and the 2nd Value Field would be Original Estimate - with the new option only the filtered team members will be populated with the estimated hours as a second value.
Improvements:
- Greatly improved the support for visualization of negative values.
- Fixed an issue that caused the Exply UI to throw an error when changing widget types from or to Pivot Tables.
- Exply for Jira now also allows developer licenses.
- Fixed an issue that caused the Tempo Team Role Rate to not being correctly assigned when a Tempo Team is set in an issue.
Exply 4.13.1 - Changes are visible immediately after Data Import
Improvements:
- In rare cases imported data–items (such as hours) appeared multiple times after a data import. Later everything went back to normal. Now we re-index internal data structures after a successful import immediately. Multiple and removed data–items no longer appear in Exply dashboards.
- The Widget Explorer tolerates invalid selections. If individual widgets fail to render they do not affect the other widgets.
Exply 4.13.0 - Calculations (Phase 1)
Highlight:
- Calculation (Phase 1):
- Exply finally allows you to extend your data with calculations! We have used the last couple of months to restructure and prepare Exply for this big new feature and still have a lot to do. Therefore, the complete calculation feature will be released step by step. In phase 1, you will be able to:
- Calculate Value Fields with constants in all four basic arithmetic operations, e.g. calculate the turnover by multiplying the billable hours by the hourly rate of the project.
- Add or subtract two Value Fields, e.g. subtract the billable hours from the total logged hours to get the amount of non-billable hours in your issues/projects.
- Exply finally allows you to extend your data with calculations! We have used the last couple of months to restructure and prepare Exply for this big new feature and still have a lot to do. Therefore, the complete calculation feature will be released step by step. In phase 1, you will be able to:
Further Features:
- Add reference lines to the Time Series Charts and Row/Bar Charts to easily visualize thresholds, min & max. values, etc.
- It is now possible to directly download all necessary logs without the need of navigating to the internal logs folder. This will make it a lot easier for the Exply support to provide direct help.

Improvements:
- Improved the import behaviour for Tempo Teams. If an issue is not directly assigned to a Tempo Team the team of the assignee will be connected.
- Fixed an issue that caused the import to fail due to not completely removed users in the Jira database
- Fixed an issue that made it necessary to reload the user interface of Exply after the first import to see new imported fields
- Fixed an issue that caused the importer status icon to turn red while the import was still running
- Various additional minor fixes and improvements under the hood
Exply 4.12.0 - Sprint Detection, Value Filter, Units, Tempo Team Programs
Features:
- New filter options: You can now add filters for dates and values. This enables you to filter e.g. issues that are not estimated, issues that have logged hours above a certain amount, and way more.
- Exply now imports Tempo Programs for Teams
- You can now set individual units for every value and widget. This comes in handy when comparing e.g. logged hours with the logged/estimated ratio in percent.
- Exply now also automatically detects Jira Sprints in the new Sprint Burndown Chart widget.
Improvements:
- Added an option for Exply groups to also contain spaces like Jira group names
- Team commitments are now also linked to Jira Projects and Jira Boards
- Sub-Issues are now also available as Issue Type
- Long Dashboard titles now use the complete available space within the header
- Fixed an issue that prevented users from editing widget titles of widgets with errors
- Various additional minor fixes and improvements.
Exply 4.11.0 - Raw Data Table filter & Improvements
Features:
- Added the widget filter to the Raw Data Table to be more useful. You can now decide which kind of data (e.g. issues, time records, etc.) you want to see in a list.
Improvements:
- Fixed an issue that caused the importer to stop working if an invalid link was detected in the database.
- Fixed an issue that caused the whole Dashboard to show no data, if a single widget was faulty. Now only the relevant widget shows an error message.
- Fixed an issue that caused the data mapping on existing category fields in some importers to fail.
- The labels for the value "Number of entries" are now more descriptive.
- Fixed an issue that caused Jira usernames to be not shown correctly in very rare instances.
- Various additional minor fixes and improvements.
Exply 4.10.1 - Burn Down Chart & Windows Server Improvements
Improvements:
- The Burn Down Chart now features two modes. Per default, the Burn Down Chart treats different allocations (periods) in the Quota independent (Scrum Sprint mode). You can also let the Burn Down Chart sum them all up so that the allocations are handled like a project budget.
- Fixed an issue that prevented the Exply process to stop when deactivated/uninstalled/updated on Windows-based servers.
- Fixed an issue that caused Epics to be only imported as Epics, and not as issues as well.
- Added more specific improvements for Windows server environments
- Various additional minor fixes and improvements.
Exply 4.10.0 - Define import period, Tempo Workloads & Commitment
Features:
- In Exply for Jira it is now possible to define the import period in days. This way it is no longer necessary to import all JIRA (& Tempo) data, and there is a potentially enormous improvement in import speed. This is especially useful, if data doesn't change after a couple of days and you just want to update/import the last 14 days. Leaving the appropriate form blank, will import everything. You can also do a two-step setup. First of all, you import all data and after this is done you set the import period to a smaller amount. All data will be kept and only the data within the period will be updated.
- Exply for Jira now also imports Tempo workloads & team commitment. This way you can finally compare planned workloads with actually logged hours.
Improvements:
- Fixed an issue that caused the Excel export to fail on Windows servers
- Various additional minor fixes and improvements.
Exply 4.9.1 - Improvements & Bugfixes
Improvements:
- Improved the logging for Exply Core (used in JIRA)
- Improve performance of generic SQL importer preview
- Fixed an issue that caused the Excel export to fail when the temporary directory of the server is not writeable by Exply
- Various additional minor fixes and improvements.
Exply 4.9.0 - Tempo Revenue & Bugfixes
Features:
- Tempo Revenues are now calculated in Exply. They are based on billable hours and the corresponding price table. Within Exply you have the new value field "Amount of Worklog Expense" to analyse and visualise your revenues. There is also the new category field "Tempo Worklog Team Role".
Improvements:
- Fixed an issue that caused the end date form in the date picker to show the start and not the end date in the calendar.
- Various additional minor fixes and improvements.
Exply 4.8.3 - Improvements & Bugfixes
Improvements:
- Added support for ActiveCollab 6
- Fixed an issue with the Elasticsearch fields limit.
- Fixed an issue that prevented the user to configure multiple values in the pivot table widget
- Fixed an issue that prevented Exply from importing original estimates when it was changed back to 0 hours again
- Various additional minor fixes and improvements.
Exply 4.8.2 - New Booked/Estimated Ratio & Improvements
Improvements:
- Added a new calculated value field: Booked/Estimated Ratio
- This value field calculates the ratio between booked hours and the original estimate per issue, e.g. if an issue is estimated with 10 hours and it has been 7h logged to it, the ratio will be 0.7
- Please note that summing up ratios will not bring up useful results. This value field works best if used in the Metrics Tile Widget with the average-operation, or any other Widget when the data is categorised on issue-level, e.g. with "Issue" and "Issue Key".
- Added way better error handling
- Added an error screen with the option to send a bug report to our support
- Filters are now represented in Pivot Table Widget column names
- Improved the x-axis tick marks in Time Series Widgets
- When editing an existing Widget the corresponding period is now used in the Widget Configurator as well.
- Fixed an issue that caused a small display-bug when the Search-Widget was used with a Widget title
- Fixed an issue with importing Tempo Teams in Exply On-Premise
- Fixed an issue with the scrolling position
- Fixed an issue that caused Exply to crash when users added Widgets via the Widget Explorer and then decided to switch to the Advanced Configuration
- Fixed an issue that prevented closing the Quota Tile Widget details on small screens
- Fixed an issue that prevented some tooltips to be displayed correctly
- Updated the internally used Elasticsearch to 7.4.2
- Various additional minor fixes and improvements.
Exply 4.8.1 - Importer Performance Improvements
Improvements:
- Performance of all SQL-based Data Source Importers has been greatly improved
- Added percentage option to the Bar Chart widget
- Fixed an issue with the handling of Tempo Teams
- Fixed an issue that caused a grey screen when selecting a future date with the keyboard
- Various additional minor fixes and improvements.
Exply 4.8.0 - Generic SQL-Importer, Federated Jira, Quick Filter Widget, Tempo Planned Time & Expenses
Highlights:
- We've completely rewritten Jira Server & Tempo Importer for Exply On-Premise. It allows users to import data from unlimited Jira Server instances (federated Jira) including Tempo Timesheets. This way users are also able to combine their Jira data with additional data like time tracking, ERP or CRM at once and analyze them all in one place.
- Exply now features an all-new generic SQL-Importer for MySQL, MariaDB, PostgreSQL, MS SQL and Oracle.
To make the SQL statement writing as fun as possible, the SQL-Importer comes with syntax highlighting, auto-completion and a preview of your selected data :)
Features:
- Quick Filter Widget
Quick Filters allow you to simply assign data selections and make them accessible via this new widget type in any Dashboard. For instance, you can add specific filters for projects, people, teams, sprints etc and activate them with one click. You can also add drop-downs with no specific data selected by leaving the filter blank. - Added a new XML-Importer
- Greatly improved the support for more formats in field mapping suggestion during importer configuration
- Added Tempo expenses and planned time to the Jira importer
Improvements:
- Easier Configuration UI for JIRA importer (on Premise)
- Redesigned the data source importer screen
- Fixed the styling and auto focus for importer preview and CSV importer
- Added way more helpful error messages in generic importer previews
- Fixed a styling issue for smallest values in the Matrix Chart
- Fixed a bug that caused the Excel export to fail, when widget groups had the same name
- Fixed a bug that caused the 3-dot menu to be not shown when long Dashboard titles were used
- Fixed a bug that caused the TimeSelector to not refresh the second date field when the preset time span was changed in edit mode
- Fixed a bug that prevented the user to change the granularity in Timeline charts when no widget title was given
- Various additional minor fixes and improvements.
Exply 4.7.0 - Customizable CSV Import
Highlight:
- Exply imports a much wider range of CSV formats. You can configure custom separators, quotes, file encodings and much more.
Feature:
- The labels of bars in the Row Chart and the Bar Chart show the values of the bar in percent now. The sum and the percentage are visible side-by-side after the update.
Improvements:
- A number of small and big impediments regarding the upload and import of CSV files have been solved.
- Data Imports in general are more stable, especially on systems under high load.
- Some advanced settings for the Time Series Charts work again.
- Various additional minor fixes and improvements.
Exply 4.6.1 - Microsoft SQL Server Support
Improvements:
- Exply can access the Tempo data in Microsoft SQL Server databases now.
Exply 4.6.0 - Java 11 Support
Highlight:
- Exply runs in Java 11 and Java 8 now. Other Java version might work as well though they are not officially supported.
Features:
- The time selector got an "All Time"-Option which enables you to see all your data independent from a date.
- Moreover, we added a "This Quarter"-Option to the time selector.
Improvements:
- If we can't access your Tempo database then we just use the JIRA data. This way at least issues and projects are available.
Exply 4.5.0 - Gantt Chart and more Fields
Highlight:
- Specifically to visualise Issue Status Changes, we provide a Gantt Chart. Of course it can show other data as well.
- Exply supports more fields, especially Project Category, Issue Resolution, Votes, Watches, Sprint Name and Sprint Status.
Features:
- Exply more clearly differentiates between Epics, Issues and Sub–Issues. In special cases, dashboards might show different, more intuitive results.
- Time Series Charts sum up the values if you like them to: Compare the sum of created vs. resolved Issues over time.
Improvements:
- Names and labels are more intuitive.
- If you upload custom Icons for your dashboards, they now last more than one hour.
- The Time Selector allows to select "Last Working Day" again.
- We import the Tempo Account and Tempo Customer for Issue without Work Logs.


Exply 4.4.0 - New Dashboard Screen and Jira Fields
Highlight:
- Exply now comes with an all-new start screen that gives you direct access to all your Dashboards. No more fiddling around with the slide-out dashboard menu.
- You can also mark Dashboards as favourites to gain even faster access and add custom images to Dashboards via the three-dot menu.
Improvements:
- Fixed an issue that prevents the image widget upload in Exply for Jira.
- Improved the styling of all text and added more icons in the UI.
- Added missing Jira & Tempo fields and checked Field Naming in Exply
- Enabled the option to add axis descriptions for Matrix Chart
- and way more

Exply 4.3.1 - Name and Email of Creator for all Work Logs
Improvements:
- Fixed a bug that caused inconsistency for some users. In rare cases Exply showed (empty value) instead of the correct user name and email for logged hours. This only affected some user.
Exply 4.3.0 - Import status changes of Jira issues
Highlight:
- Exply now imports status changes of Jira issues. This allows you to create analytics that answer questions like How long was the ticket in the "open" phase? How long does it take until we respond to critical customer issues? How often was the status changed of issues? Or you can analyze the time in status by assignee and way more.
Improvements:
- Fixed an issues that caused the Exply importer to fail while trying to import data from PostgreSQL databases
- and more
Exply 4.2.0 - Widget Explorer
Highlights:
- Completely redesigned the Widget creation in Exply with the all new Widget Explorer.
Simply select the values you're interested in and the Exply Widget Explorer suggests fitting analytics. The clou: you are always in full control. Already know what you want? Just switch to the "Advanced Configuration". Not sure yet? Experiment with your values, browse the different Widgets and add your favorite ones. You can also configure recommended Widgets at any time.
Improvements:
- Multi Value filter in Pivot table now works as expected if two or more value filters start with the same filtered item
- Row & Bar Chart now also work perfectly with the same value field filtered multiple times in different ways.
- Added support for PostgreSQL in JIRA Add-On Importer
- More verbose logging after Exply installation
- and more


Exply 4.1.0 - User Management for JIRA & Excel Export Permission
Highlights:
- Decide which JIRA user or group can use Exply and fine-tune what is visible to whom.
- Remember to grant someone access to Exply after updating - Exply is no longer visible to anybody by default.
Features:
- Only Administrators can change critical settings in Exply and use the fine-grained Raw Data Excel Export.
- A preconfigured Analysts group allows to access all data in Exply and configure Dashboards.
- The Team Member group restricts access to own Work Logs and all Issues. Dashboards interact but cannot be edited.
- Use the default permission configuration or create your own one tailored to your needs.
- You can reuse your existing JIRA groups for Exply – no need to create new ones in JIRA.
- You can grant customers access to single Dashboards showing only what you can show.
- You can override the permissions of single JIRA users regardless of their group memberships.
- You can grant or deny the full Raw Data Excel Export.
- Use the shipped default configuration or consult our documentation.
Improvements:
- Excel Export more stable, for dashboard results and raw data
- more minor fixes and improvements
Exply 4.0.0 - Major Release
Highlights:
- One generic data type to make comparing even easier - no need to filter for data/document types anymore!
- Direct database import for Tempo Timesheets - way faster and no extra permissions needed.
Features:
- All imported data fields are now distinct fields. For examples, you can now differentiate between Worklog Created On and Issue Created On. This also applies to many other fields.
- Value Field Filters within every Widget. It is now finally possible to set individual filters in each Widget and directly compare different data.
- Interactive Burndown Chart
- Duplicate Widgets & Dashboards
- Sum Row/Column for the Matrix Widget
- Added the option to set a custom timespan as default in the Time Selector widget
- Added more default time spans to the Time Selector widget (e.g. last 7 days, last 2 weeks, last 3 months, etc.)
- Added option for non-encrypted logins to Exply On-Premises
Improvements:
- Some Row Chart did not show tick descriptions
- Add more default formats for the CSV importer
- Tick labels are now centered in Row Charts with multiple values
- Editing and saving Dashboards in responsive mode caused them an to stay in responsive size, even when the Dashboard was normal size again
- Fixed an issue with the number picker in widgets
- Fixed an issue that caused Jira gadgets with predefined height to not work correctly
- and many more
Exply 3.22.0 - Tempo Importer Improvements & Bugfixes
Features:
- You can now set the size of Exply gadget on JIRA dashboard & autosizing.
Improvements:
- Fixed an issue with an undocumented Tempo API Change introduced with Tempo 9 that caused the Exply Tempo importer to import billable hours as non-billable hours.
- Improved Row Chart and Time Series Chart to properly visualize negative stacking values.
- Preparing Exply for major release of version 4.0. Integrated config backups when updating to version 4.x.x to allow downgrades to version 3.22.0
- additional minor fixes
Exply 3.21.1 - Improvements & Bugfixes
Features:
- The option to set a start date for the Tempo Importer in JIRA is back. If you don't want to import the complete history of your Tempo worklogs you can now define a date to start from.
- Improved the Setup Wizard for Exply On-Premise
- Estimates from ActiveCollab are now imported
Improvements:
- Improved the visibility of the delete confirmation within widgets
- Improved the Dashboard filter styling on small screens and small JIRA dashboards
- Improved the loading animation for dashboards to be more visible when new data is being loaded
- Fixed the shadow-color of red buttons
- Fixed some paths in the Debian daemons config files
- Fixed an issues with the login via Crowd
- Fixed an issue for FreeBSD deployment
- Fixed an issue that prevented the Time Selector widget to show available time spans correctly
- additional minor fixes
Exply 3.21.0 - Legend Option for Bar/Row Charts & Bugfixes
Features:
- Bar and Row Charts now also come with a legend option in the settings, that can be enabled or disabled by default.
- You can now directly change the granularity of the Time Series widget from the dashboard view by simply selecting a different one (day, week, month, quarter, year) in the upper right corner.
Improvements:
- JIRA custom field date is now imported as a da and not as category, so it can be used in timeline charts
- Removing the required pivot-field from a widget now prompts the user to select a pivot field instead of the red error message.
- Fixed a bug that caused the Quota widget to display "time frame in past" when no time frame selected.
- Improved the delete-confirmation modal for widgets. It is now shown directly within the selected widget.
- The data type of widget groups can now be deleted again.
- additional minor fixes
Exply 3.20.1 - Multi-Value Time Series Chart & Bugfixes
Features:
- Replaced the classic Time Series Chart with the all-new Multi-Value Time Series Chart. You can now add multiple values into one chart to compare them easily by using different visualizations like bars, area and lines (e.g. income vs. expenses, logged vs. billable hours, billable hours vs. income). Different values can be allocated to different axes. For each chart component there are several options to customize them. Note: All existing Time Series Charts have automatically been migrated to the new one.
- Note: All existing Time Series Charts have automatically been migrated to the new one.
Improvements:
- Added a hint why Dashboards can't be saved
- Fixed an issue that prevented the Metric Tile Widget to show a result
- Fixed an issue that didn't allow Firefox users to use multi-select in charts
- additional minor fixes
Exply 3.19.1 - Minor Fixes & Improvements
Improvements:
- To improve widget configuration and prevent double counting, all available values can only be selected once per widget.
- Fixed an issue that caused the datepicker/selector to show wrong dates in some cases
- Fixed an issue that prevented the Quota Tile configuration to work as expected
- Fixed an issue that prevented the leave confirmation to be shown
- Fixed an issue that prevented the Document-Type-Selector to be shown when a new Dashboard was created
- additional minor fixes
Exply 3.19.0 - New Time Selector & Improvements
Features:
- Added a new nicer Time Selector which is now working in all browsers perfectly. It also comes with more predefined time spans like quarters and penultimates. Because of the long list of presets, users now have the option to select their favorite time span presets to be shown.
- Time Series Charts now also come with year and quarter as granularity.
Improvements:
- Replaced the Ratpack webserver with Spring Boot
- Fixed an issue that prevented JIRA labels from being shown
- additional minor fixes
Exply 3.18.0 - Support for JIRA Gadgets & more default Dashboards
Features:
- Added support for JIRA Gadgets (Version 7 & 8). JIRA users can now easily add every Exply Dashboard/Report to their JIRA Dashboards. All functionalities like global search, interactivity, filters, selections, responsiveness etc. are supported.
Improvements:
- Added more Default Dashboards to explore
- Fixed a minor display-bug in the Quota Tile
- additional minor fixes
Exply 3.17.5 - JIRA 8 Compatibility & Bugfixes
Improvements:
- Added Compatibility to JIRA 8 for Exply for JIRA.
- Fixed a bug that prevented new widgets to get a correct default height and width
- Fixed several React bugs
- additional minor fixes
Exply 3.17.4 - Minor Improvements & Bugfixes
Improvements:
- The original Row Chart has been separated into Bar Chart and Row Chart
- Widgets now have minimum sizes to prevent strange visualization
- Fixed a bug that caused the header in row and bar chart to disappear
- Fixed the Widget Edit Mode on small screens
- Fixed a bug where negative values with stacking were rendered in the positive direction
- additional minor fixes
Exply 3.17.3 - Minor Improvements & Bugfixes
Improvements:
- "Remove" importer button has been moved to the importer overview right beneath "clear data"
- Improved the default labels for predefined document fields in Exply for JIRA add-on
- "Save & Sync" button in Exply for JIRA has been moved up to be more visible
- Fixed an issue that resulted in an empty Exply screen when clicking "Create New" from the JIRA Exply Menu
- Fixed an issue with Windows servers preventing Exply for JIRA to be installed correctly
- Improved styling for Firefox
- additional minor fixes
Exply 3.17.2 - Treemap Widget Labels & Bugfixes
Features:
- Added option to display values in big enough Treemap Widget tiles
Improvements:
- Cleared all document types and fields having no sample data for demo.exply.io and Exply for JIRA
- Fixed a bug that didn't allow users to enter "10" as the number of bars in Row & Bar Charts
- Improved error logs if start of importer process failed
- additional minor fixes
Exply 3.17.1 - Ubuntu & Debian Packages, Bugfixes & Improvements
Features:
- Packages for Ubuntu 18, 16 and Debian 9
Improvements:
- Timeline Chart in Area-Mode now also shows the selected time span, just like in Bar-Mode
- Fixed number of decimals in Row & Bar Chart
- Fixed import of Work Logs from Tempo Timesheets when billable time is greater than logged time
- Improved styling for Quota Tile, especially text size
- additional minor fixes
Exply 3.17.0 - Selectable Timeline Chart, Improved Quota Tile, Pivot-Functionality for Bar Charts, Line Chart, Scatter Plot
Features:
- Timeline Chart now features selections. Seeing something suspicious in your time series data? Just click the corresponding time entry, or time span by holding shift to drill down.
- Improved Quota Tile now states why it shows no quota, e.g. quota exceeded, past time span. By clicking the little info icon in the Quota Tile reveals additional info about the shown result.
- Added pivot-functionality to Bar Charts
- Added new Line Chart Widget
- Added new Scatter Plot Widget
Improvements:
- Improved value labels for huge numbers, e.g. Kilo, Million, Billion
- Long widget titles now overflow on hover
- Tooltips are now indicated by blue beacons and don't show up all at once
- Added option to deactivate the Chat completely through the main menu
- Fixed an off-by-one error in expected working time in Quota Tile
- Fixed an issue that caused the importer to crash
- Fixed a bug that Exply didn't ask to save Dashboards in edit mode when clicking on Exply logo in the header
- additional minor fixes

Single Selection

Multi Selection (Ctrl-Shift)
Exply 3.16.1 - Styling and Usability Improvements
Improvements:
- In edit mode, the Widget configurations are now saved when switching between widgets, to allow quick comparison between different visualization types
- The value field is now required to ensure better control over the shown analytics. We're also migrating all your existing widgets to the new format.
- Removed the modal that asked to save changes, when no changes have been made in edit mode.
- Unified the Widget edit mode and made the order of the configuration fields more straightforward and consistent
- Number of Entries is now a separate option to choose as a value
- Added thousands separator to all values with the option to change them in My Profile
- Added slight transparency to mouseover tooltips in widgets, to improve visibility and navigation
- Improved styling for Timeline Chart labels
- additional minor fixes
Exply 3.16.0 - Sunburst Pie Widget, CSV Import & new Metrics Tile Options
Features:
- Added a new Sunburst Pie Widget to help you visualize your data in even more beautiful ways. Like the Treemap Widget, the Sunburst Pie is very useful to show the relationship between all elements. You can also use it as a temporary filter by selecting a single element or using ctrl-click to select multiple tiles.
- Finished the new CSV Importer originally introduced in Exply 3.14. You are now able to import every CSV file through the Importer settings and configure it completely within Exply.
- Metrics Tile Widget now provides Min, Max, Average and Count functionality in addition to Sum. We also improved the overall styling.
Improvements:
- Added the option to define a default sorting in Row/Bar Chart widgets. This also includes the possibility to choose whether the widget should show the top (default - by value descending) or flop (by value ascending) data.
- Since Dashboard titles are required (Exply 3.15.0) they are now automatically selected, so that you can immediately start typing after adding a new Dashboard
- Updated all Widget icons to be even more beautiful
- Fixed the styling of the importer overview
- Fix a bug in the license management where licenses without limit didn't allow new users to be added
- Disabled repeat button in quota tile when there is nothing to repeat
- Search in Dashboard selector now shows 'No Search Results' for empty search results
- Empty dashboards now look better
- Fixed position of floating action button
- Added modal if a user wants to delete a widget group
- Fixed a bug that caused the Exply UI to crash when the "Repeat for next time span" button in the Quota Tile Widget was pressed very fast consecutively
- additional minor fixes
Exply 3.15.0 - Treemap Widget & Improvements
Features:
- Added a new Treemap Widget to visualize your pivot data in an even more beautiful way. Just click on a single tile to select it and use it as a temporary filter for your dashboard. You can even use ctrl-click to select multiple tiles.
- Row Charts now have the option to sort the bars by name or value (asc., desc.)
Improvements:
- Moving the cursor over the Row Chart now indicates even better, that single or multiple (ctrl-click) bars can be used as temporarily filters
- Dashboard title is now required so that they can be identified faster and easier
- Improved the overall styling of the Row Chart Widget
- Fixed a bug causing umlauts in result table export to be broken
- Put the widgets in a better order when adding a new one
- Integrated usage analytics to help us improve the user experience
- Added My Profile to the main menu to view usage analytics
- additional minor fixes

Exply 3.15.0 features the new Treemap Widget & Sorting for Row Charts
Exply 3.14.0 - Matrix Chart & CSV-Import (Preview)
Features:
- Added a new Matrix Chart to allow correlations between two categories (e.g. Count of Issues per Issue Priority and Name of Developer)
- Added a new CSV importer (not included in Exply for JIRA) with automated data mapping. We will add additional manual data mapping options in the next release.
- Added vertical view option for the Bar Chart widget
Improvements:
- Dashboard title is now required so that they can be identified faster and easier
- Fixed the Importer Icons to be inline and in the right aspect ratio
- Rearranged the context menu icons, to get instant access to the primary actions like editing Dashboards or moving Widget Groups up and down. All further actions are stored in the 3 dot menu.
- Moved tooltips toggle to global header
- Updated cursor for menu items and switch labels
- additional minor fixes

Exply 3.14.0 features the new Matrix Correlation Chart & vertical Bar Charts
Exply 3.13.0 - Tooltips, Live Chat & much more Help
Features:
- Added Tooltips to make it even easier to unlock the value in your data (can be de-/activated via the main menu or through the little bulb-icon at the top of each dashboard)
- Added a Live Chat to make it even easier for you to get in touch with our support team
- Changed the JIRA navigation entry from Exply to Charts & Reports and added options to directly open existing and create new dashboards
- Added an Initial Configuration Wizard to the Exply On-Premises version to make the first steps with Exply even easier
Improvements:
- Added a help section to the startscreen for direct access to useful tipps as well as the latest changes to keep you updated
- Improved JIRA configuration screen including a new video tutorial on how to setup up the Tempo importer
- additional minor fixes
Exply 3.12.2 - New Quota Tile Feature & Improvements
Features:
- Quota Tile Widgets now allows users to continuously add new months without the need of setting them manually
Improvements:
- Fixed a bug which caused the Quota Tile to crash while editing after the React update
- Fixed a bug which caused the Importer setup to crash after the React update
- additional minor fixes
Exply 3.12.1 - Minor Fixes & Improvements
Improvements:
- Added and improved action button title tags
- Widgets now show "no data", if there is nothing to show for the selected parameters
- additional minor fixes
Exply 3.12.0 - Improved Usability, Speed & Design
New Features:
- Added import of custom Tempo fields
- Added licensing model for Exply on Premises
- Added System Information showing version and license
- Updated ActiveCollab importer to work with versions 3, 4 and 5
- Added Importer Status widget to see directly, if the shown data is up-to date
Improvements:
- Compatibility to JIRA 7.10.2
- Completed a full React update
- Improved the filter functionality of widget groups through a new 'Add Filter' button
- Widgets can now be removed directly from the dashboard
- Improved "My Profile"
- Importer logs now contain date
- Improved formatting of custom JIRA fields
- Selecting a different dashboard while editing a widget prompts a warning
- Row Chart Widgets use short labels per default
- Changing the default time selection now shows the new time span immediately
- Improved the behaviour of the time selector widget to prevent change of end date when setting start date and vice versa
- Changed Plus Icon in Row Chart Header to Filter Icon to make function more clear
- Fixed Startscreen Menu Entry closes Dashboard Selector
- Improved all used icons & removed unused font files
- Restyled User Management
- Disabled Guided Tour for the time being - will be replaced by a better one
- Improved the widget editor style
- Widget edit buttons are now only shown on hover
- Duplicating a widget group scrolls down to the duplicated one
- Snackbar notices about successfully duplicate widget group
- Changed the widget resize handler
- Promoting a widget group to be a global group moves it automatically to the top
- Made widget preview in editing mode more clear
- Restyled "Add new Widget" button
- Added a confirmation dialog to cancel dashboard editing
- Added link to startscreen in menu
- Moved save/cancel buttons to footer when editing dashboards
- Changed label of reset button to "reset filters"
- Additional minor bugfixes and improvements
Exply 3.11.0 - Multi-Value Row Charts
New Features:
- Row charts now allow to display multiple value fields
- Short labels for row charts
Improvements:
- Added option to display dashboards in selector as a list
- Changed shadow color of dragged widgets
- Allow to manually start data import between 0 and 1 AM
- Tour uses only field which should be always available
- Updated QuoJob Data Source
- Fixed row chart tooltips labels for stacks
- Removed unused fonts from CSS and installation file
Exply 3.10.2 - Improved Handling of Tempo Custom Fields
Improvements:
- Previous Versions could cause not all Tempo Custom Fields to be imported correctly
Exply 3.10.1 - Minor fix for some Field IDs
Improvements:
- Fixed an issue where some fields containing dots in the ID, e.g. "created_by.name" haven't been updated always
Exply 3.10.0 - JIRA Custom Fields
New Features:
- Added support for all JIRA Custom Fields
Improvements:
- Minor Bugfixes
Exply 3.9.0 - Table Widget
New Features:
- Added the new Table Widget
- Added support for default date formats during XML import
Improvements:
- Fixed typo in logging
- Made XLSX export robust against extreme long text values
- Updated elasticsearch to 2.4.0 to be compatible with jackson 2.9.4
- Some additional minor bugfixes
Exply 3.8.0 - Guided Tour & Windows Host fixes
New Features:
- Added "Last Working Day" to the Time Selector Widget, working days can be defined in the widget configuration
- Added a Welcome Tour for first time users
Improvements:
- Fixed an issue that caused Exply to run in recovery mode on Windows hosts
- Fixed an issue with overlaying dropdown menus
- Some additional minor bugfixes
Exply 3.7.1 - Critical JIRA Bugfix
Improvements:
- Fixed a critical bug that sometimes prevented Exply from starting when it was installed the first time within JIRA
- Some additional minor bugfixes
Exply 3.7.0 - New Filters & Bugfixes
New Features:
- Completing the filter options, you're now able to also set not-filters like equals not, to exclude certain projects, people, issues, epics, etc.
- Filter for (empty value)
Improvements:
- User Manager suddenly wouldn't allow to change single permissions
- Additional warning before disabling/removing his account
- Last admin cannot disable his admin role
- Fixed a bug that sometimes blocked deleting a dashboard
-
Fixed the quota tile to display the correct date range
- additional minor bugfixes
Exply 3.6.1 - Improvements
Improvements:
- Better Color for not selected chart bars
- Current dashboard is now highlighted in the dashboard selector
- Fixed strange behaviour of opened dropdowns
- Maximum Number of displayed chart bars and stacking was off by one
Exply 3.6.0 - Raw Data Export
New Features:
- In addition to the basic Excel export you can now also export the original raw data. The exported data reflects the dashboard including the applied filters for projects, people, issues, etc.
Improvements:
- Compatibility to JIRA 7.8.0
- Tempo Data Source was sometimes marked as erroneous
- Corrected the hover legend in time line chart
- Fixed back to JIRA button
- Fixed bug when duplicating a widget group
- Other minor bugfixes
Exply 3.5.0 - Excel Export
New Features:
- Export your dashboards to Excel Spreadsheets. The selected filters, projects, people, etc. form the basis for exporting your data.
Improvements:
- minor bugfixes
Exply 3.4.0 - More Operators, Filters, Full-Text Search, Improved User Management
New Features:
- Directly find the dashboard you need with the Dashboard Selector Filter
- Filter for Widgets, Groups and Dashboards now also provide: contains, ends with, matches, starts with
- Select data in row charts using the full-text search
- Check if data context is configured correctly for new users by switching into the user role
Improvements:
- Fixed background scrolling in widget editor and dashboard selector
- Significant reduce of disk consumption
- JAVA memory settings tweaked
- Notification when deleting a dashboard
- Selected labels in row chart bars are now highlighted
- Login page styling fixed
- JRE in Debian package by dependency replaced
- Current user in user list is now highlighted
- Users with no name are rendered correct in user-list
- Better and more simpler caching
- Importer configurations with invalid schedule are now being rejected
- Incomplete filter configs are now highlighted and the save button is disabled
- Widgets now show the sum of values within
- And more minor improvements
Exply 3.3.0 - Image Widget & Custom Quota Tile Color
New Features:
- New Image widget to add custom images to your dashboards and reports
- Color selection for Quota Tile allows you to select a custom color or set it automatically
Improvements:
- Increased number of suggestions within autocompletion
- Drop downs are sorted ascending by label
- All widget groups and dashboards are automatically created with Time Selector widget
- Notification if your session has expired
- and more minor improvements
Exply 3.2.0 - Production Release
We're proud to announce the Exply for JIRA Production Release, including:
- Drag-and-drop Dashboards for your JIRA & Tempo Data
- Individual Reports for your Projects
- Various Types of Charts
- Easy Setup
and much more!
Exply 3.1.0 - Better JIRA Integration and much more
New Features:
- Support of Windows Server Machines
- Labelling of Fields match JIRA names
- Specialized Dashboard-Styling for Printing/PDF Export
Improvements:
- Button to start Data Import manually
- More appealing Colors
- full support of special characters
- Filter for "(empty value)"
- all fields to JIRA issues
- all fields to Tempo Worklogs
- Styling-improvements and fixes of glitches
- better overall Performance
Exply 3.0.4 - Importer & Stability Improvements
Improvements:
- Automatically disable Tempo importer if API Key is empty
- Improved tooltip for Timeline Bar Chart
- Reload Data if returning to last opened Dashboard
- Improved Stability
Exply 3.0.3 - Auto-Recovery
Improvements:
- Colored Legend for Stacked Bar Charts and improved rendering
- Advanced JIRA configuration and status information
- Option to ignore SSL errors (not recommended)
- Auto-Recovery and error diagnose screen if Add-On does not work
Exply 3.0.2 - UX/UI Improvements
Improvements:
- Dashboards don't disappear randomly anymore
- Local config not removed if add-on restarts
- Better UX/UI for Pivot Tables on Smartphones
- Button to create dashboards on welcome screen is now hidden on mobile devices
- Ellipses for long titles
- Improved pivot-table support in small screens
- Faster add-on start-up
Exply 3.0.1 - Minor Bugfixes
Improvements:
- Minor Bugfixes
Exply 3.0.0 - Initial Release
You may think "Wait a second! The initial Exply Release is 3.0.0? What happend to 1.0 and 2.0?" and you're absolutely right! It seems a little bit strange starting a release this way.
But this semantic versioning is based upon the internal history of Exply. Some of our befriended customers used to run an earlier version on their systems, like we did to achieve very specific tasks.
The goal of Exply version 3 was to be much more versatile in its data handling and visualisation. It's also way easier to talk about Exply, if the versioning is consistent, so that we always speak of the same thing.
And that's basically it :-)